California Permit Streamlining Act Deadline Calculator

Enter the date a California city or county received a development application, or the date of any later step, to see when each statutory period ends: the completeness review, the appeal, the approval decision, the SB 330 preliminary application dates and the Housing Accountability Act's consistency notice. Each result shows the statute's own sentence and its subdivision.

These are the statute's periods counted from the dates you enter. Extensions, resubmittals, tolling and the project's facts change real deadlines.

Enter a date for any event that has happened. Each result is that date plus the number of days the statute states. The date you enter is not counted and the last day is, as Government Code §6800 provides: “The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded.”

  1. Completeness: the first determination

    The agency determines in writing whether the application is complete. 30 calendar days, Gov. Code §65943(a).

    Enter the date above to see when this period ends.

    The statute's words: “Not later than 30 calendar days after any public agency has received an application for a development project, the agency shall determine in writing whether the application is complete and shall immediately transmit the determination to the applicant for the development project.”

    If the written determination is not made within 30 days after receipt, and the application includes a statement that it is an application for a development permit, the application is deemed complete for purposes of the chapter (§65943(a)). The applicant and the agency may agree to extend any time limit in the section (§65943(d)).

  2. Completeness: after a resubmittal

    The agency determines in writing whether the application as supplemented or amended is complete. 30 calendar days, Gov. Code §65943(a), (b).

    Enter the date above to see when this period ends.

    The statute's words: “Upon receipt of any resubmittal of the application, a new 30-day period shall begin, during which the public agency shall determine the completeness of the application. … Not later than 30 calendar days after receipt of the submitted materials described in subdivision (a), the public agency shall determine in writing whether the application as supplemented or amended by the submitted materials is complete”

    If the written determination is not made within that 30-day period, the application together with the submitted materials is deemed complete for purposes of the chapter (§65943(b)).

  3. Completeness: appeal of a determination that the application is not complete

    The agency makes its final written determination on the appeal. 60 calendar days, Gov. Code §65943(c).

    Enter the date above to see when this period ends.

    The statute's words: “There shall be a final written determination by the agency on the appeal not later than 60 calendar days after receipt of the applicant’s written appeal.”

    If the final written determination on the appeal is not made within that 60-day period, the application with the submitted materials is deemed complete for the purposes of the chapter. An appeal permitted to both the planning commission and the governing body does not extend the 60-day period (§65943(c)).

  4. After a preliminary application: the development application

    The development proponent submits the application for the development project. 180 calendar days, Gov. Code §65941.1(e)(1).

    Enter the date above to see when this period ends.

    The statute's words: “Within 180 calendar days after submitting a preliminary application with all of the information required by subdivision (a) to a city, county, or city and county, the development proponent shall submit an application for a development project that includes all of the information required to process the development application consistent with Sections 65940, 65941, and 65941.5.”

  5. After a preliminary application: supplying what the agency says is missing

    The development proponent submits the specific information needed to complete the application. 90 days, Gov. Code §65941.1(e)(2).

    Enter the date above to see when this period ends.

    The statute's words: “the development proponent shall submit the specific information needed to complete the application within 90 days of receiving the agency’s written identification of the necessary information. If the development proponent does not submit this information within the 90-day period, then the preliminary application shall expire and have no further force or effect.”

  6. Housing Accountability Act: the agency’s written documentation of any inconsistency

    The local agency gives the applicant written documentation of each provision it considers the project inconsistent with, and why. 30 days, Gov. Code §65589.5(j)(2)(A)(i).

    Enter the date above to see when this period ends.

    The statute's words: “Within 30 days of the date that the application for the housing development project is determined to be complete, if the housing development project contains 150 or fewer housing units.”

    If the local agency fails to provide the documentation, the project is deemed consistent, compliant, and in conformity with the provision (§65589.5(j)(2)(B)). “Determined to be complete” means the applicant has submitted a complete application pursuant to §65943 (§65589.5(h)(10)).

  7. Permit Streamlining Act: the lead agency approves or disapproves the project

    The lead agency approves or disapproves the project. 180 days, Gov. Code §65950(a)(1).

    Enter the date above to see when this period ends.

    The statute's words: “One hundred eighty days from the date of certification by the lead agency of the environmental impact report, if an environmental impact report is prepared pursuant to Section 21100 or 21151 of the Public Resources Code for the development project.”

    A failure to act to approve or disapprove within the time limits required by the article is deemed approval of the permit application (§65956(b)). The applicant and the agency may agree in writing to an extension (§65950(b)).

Nothing you enter is stored or sent anywhere; the dates are worked out in your browser and are gone when you leave the page.

The periods at a glance

  • Is the application complete? 30 calendar days from receipt; a new 30 calendar days after each resubmittal (§65943(a), (b)).
  • Appeal of an incompleteness determination: 60 calendar days from the written appeal (§65943(c)).
  • Approve or disapprove: 180, 90, 60, 30 days, depending on the environmental review (§65950(a)(1) to (7)).
  • After an SB 330 preliminary application: 180 calendar days to file the full application; 90 days to supply what the agency says is missing (§65941.1(e)).
  • Housing Accountability Act consistency notice: 30 days for 150 or fewer units, 60 days for more (§65589.5(j)(2)(A)).

Every period, what starts it and where it is

The application periods in Government Code §65943, §65950, §65956, §65941.1 and §65589.5. The first 14 rows are the periods the calculator counts; the last three are stated in the same sections but are not counted by it.
What must happenPeriodWhat starts itGov. Code
The agency determines in writing whether the application is complete30 calendar daysDate the public agency received the application for the development project§65943(a)
The agency determines in writing whether the application as supplemented or amended is complete30 calendar daysDate the public agency received the resubmittal, or the materials submitted in response to its list§65943(a), (b)
The agency makes its final written determination on the appeal60 calendar daysDate the agency received the applicant’s written appeal§65943(c)
The development proponent submits the application for the development project180 calendar daysDate the preliminary application was submitted with all of the information required by §65941.1(a)§65941.1(e)(1)
The development proponent submits the specific information needed to complete the application90 daysDate the development proponent received the agency’s written identification of the necessary information§65941.1(e)(2)
The local agency gives the applicant written documentation of each provision it considers the project inconsistent with, and why: 150 or fewer housing units30 daysDate the application for the housing development project was determined to be complete§65589.5(j)(2)(A)(i)
The local agency gives the applicant written documentation of each provision it considers the project inconsistent with, and why: More than 150 units60 daysDate the application for the housing development project was determined to be complete§65589.5(j)(2)(A)(ii)
The lead agency approves or disapproves the project: (a)(1) Environmental impact report prepared for the development project180 daysDate the lead agency certified the environmental impact report§65950(a)(1)
The lead agency approves or disapproves the project: (a)(2) Environmental impact report prepared for a housing development project as defined in §65950(c)90 daysDate the lead agency certified the environmental impact report§65950(a)(2)
The lead agency approves or disapproves the project: (a)(3) Environmental impact report, housing development project, at least 49 percent of units affordable to very low or low-income households and every condition in (a)(3)(A) to (C) met60 daysDate the lead agency certified the environmental impact report§65950(a)(3)
The lead agency approves or disapproves the project: (a)(4) Negative declaration completed and adopted60 daysDate the lead agency adopted the negative declaration§65950(a)(4)
The lead agency approves or disapproves the project: (a)(5) Project exempt from the California Environmental Quality Act60 daysDate of the lead agency’s determination that the project is exempt from the California Environmental Quality Act§65950(a)(5)
The lead agency approves or disapproves the project: (a)(6) Project subject to ministerial review by the public agency60 daysDate of receipt of a complete application§65950(a)(6)
The lead agency approves or disapproves the project: (a)(7) Project exempt under Public Resources Code §21080.6630 daysThe later of the two dates in §65950(a)(7): the conclusion of the process in Public Resources Code §21080.66(b), or the expiration of the applicable time limit in §65589.5(j)(2)§65950(a)(7)
The city or county provides a preliminary fee and exaction estimate, if the preliminary application asked for one30 business daysSubmission of the preliminary application§65941.1(b)(1)
If a required public notice or hearing has not been provided or held by this point, the applicant may file an action to compel it60 days before the time limits expireCounted back from the expiration of the time limits established by §65950 and §65952§65956(a)
A petition to enforce the Housing Accountability Act is filed and served90 daysThe later of the two events named in §65589.5(m)(1)§65589.5(m)(1)

What the statute says happens when a period is missed

The completeness review. If the agency does not make its written determination in time, the application is treated as complete:

If the written determination is not made within 30 days after receipt of the application, and the application includes a statement that it is an application for a development permit, the application shall be deemed complete for purposes of this chapter.— GOV §65943(a)

The decision. If the agency does not act within the time limits of the article that holds §65950:

In the event that a lead agency or a responsible agency fails to act to approve or to disapprove a development project within the time limits required by this article, the failure to act shall be deemed approval of the permit application for the development project.— GOV §65956(b)

Two qualifications sit in the same section. Nothing in it diminishes the permitting agency's legal responsibility to provide, where applicable, public notice and hearing before acting on a permit application (§65956(d)). And where a required public notice or hearing has not been provided or held at least 60 days prior to the expiration of the time limits established by Sections 65950 and 65952, the applicant may file an action to compel it (§65956(a)). Under the Housing Accountability Act, a failure to comply with the time periods in §65950(a) also counts as disapproving a housing development project (§65589.5(h)(6)(B)). The two sections state these consequences separately and this page does not reconcile them; the Housing Accountability Act page quotes both at length.

How the days are counted

§65943 and §65941.1(e)(1) state their periods in “calendar days”; §65941.1(e)(2), §65589.5(j)(2)(A) and §65950(a) say “days”. The calculator counts every consecutive day in both cases, under the general rule in Government Code §6800: The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded. So the date you enter is not counted and the last day is. Section 6700(a)(1) makes every Sunday a holiday, so when a period ends on a Sunday the calculator also shows the following Monday.

It does not check the other holidays listed in §6700, some of which apply to a city or county only if it has adopted them (§6700(a)(20)(B)), and it does not move a Saturday: §6706 and §6707 let some acts that fall on a holiday, or filings with a state agency that fall on a Saturday, be done on the next business day, and whether either applies to one of these periods is not decided here. The 30-business-day fee estimate (§65941.1(b)(1)) and the five-working-day posting step (§65589.5(h)(6)(E)(ii)) are not counted, because the text read does not define those terms.

Extensions and what moves a real deadline

The completeness periods can be extended by agreement:

Nothing in this section precludes an applicant and a public agency from mutually agreeing to an extension of any time limit provided by this section.— GOV §65943(d)

The calculator shows each period as the statute states it, counted from the single date you enter. A resubmittal starts a new completeness period, an appeal has its own clock, and each approval period runs from a different event. The note under each result names what the statute says follows and any exception it carves out.

What changed, and what changes next

Frequently Asked Questions

How long does a California city have to decide whether a development application is complete?

30 calendar days from the day it receives the application. Government Code §65943(a): “Not later than 30 calendar days after any public agency has received an application for a development project, the agency shall determine in writing whether the application is complete and shall immediately transmit the determination to the applicant for the development project.” If it does not: “If the written determination is not made within 30 days after receipt of the application, and the application includes a statement that it is an application for a development permit, the application shall be deemed complete for purposes of this chapter.” After a resubmittal a new 30-day period begins (§65943(a), (b)), and an appeal of an incompleteness determination must be decided in writing within 60 calendar days (§65943(c)).

How long does a California agency have to approve or deny a project under the Permit Streamlining Act?

It depends on the environmental review, under Government Code §65950(a): 180 days (environmental impact report prepared for the development project; §65950(a)(1)); 90 days (environmental impact report prepared for a housing development project as defined in §65950(c); §65950(a)(2)); 60 days (environmental impact report, housing development project, at least 49 percent of units affordable to very low or low-income households and every condition in (a)(3)(A) to (C) met; §65950(a)(3)); 60 days (negative declaration completed and adopted; §65950(a)(4)); 60 days (project exempt from the California Environmental Quality Act; §65950(a)(5)); 60 days (project subject to ministerial review by the public agency; §65950(a)(6)); 30 days (project exempt under Public Resources Code §21080.66; §65950(a)(7)). Each period runs from the event the paragraph names, such as the certification of the environmental impact report or the adoption of the negative declaration, not from the day the application was filed.

What happens if the agency misses the Permit Streamlining Act deadline?

Government Code §65956(b) says: “In the event that a lead agency or a responsible agency fails to act to approve or to disapprove a development project within the time limits required by this article, the failure to act shall be deemed approval of the permit application for the development project.” The same section keeps the agency's duty to give public notice and hold a hearing where one is required (§65956(d)), and lets an applicant file an action to compel a notice or hearing that has not been provided (§65956(a)). For a housing development project, a failure to comply with the time periods in §65950(a) also counts as disapproving the project under the Housing Accountability Act (§65589.5(h)(6)(B)).

How long after an SB 330 preliminary application must the full application be filed?

180 calendar days. Government Code §65941.1(e)(1): “Within 180 calendar days after submitting a preliminary application with all of the information required by subdivision (a) to a city, county, or city and county, the development proponent shall submit an application for a development project that includes all of the information required to process the development application consistent with Sections 65940, 65941, and 65941.5.” If the agency then finds the application incomplete, the proponent has 90 days from receiving the agency's written identification of what is missing to supply it (§65941.1(e)(2)).

Do weekends and holidays count toward these deadlines?

Every consecutive day is counted. The general rule is Government Code §6800: “The time in which any act provided by law is to be done is computed by excluding the first day, and including the last, unless the last day is a holiday, and then it is also excluded.” So the day the period starts is not counted and the last day is, unless the last day is a holiday. Section 6700(a)(1) lists “Every Sunday.” among the holidays, so a period that would end on a Sunday runs through the next day. The calculator applies that Sunday rule. It does not check the other holidays in §6700 or move a Saturday.

Can the applicant and the city agree to extend a deadline?

For the completeness periods, yes: “Nothing in this section precludes an applicant and a public agency from mutually agreeing to an extension of any time limit provided by this section.” (Government Code §65943(d)). The calculator shows the periods as the statute states them, before any extension, resubmittal or tolling, so an agreed extension moves the real date.

Statute text on this page: Government Code §65943, §65950, §65956, §65941.1 and §65589.5, read November 12, 2026; Government Code §6700 and §6800, read November 13, 2026. These laws are amended most years; the dates show how current each quotation is.

Learn More

Source: California Government Code §65943, §65950, §65956, §65941.1, §65589.5, §6700 and §6800, from the Legislature's bulk data. Verify the current text on leginfo.legislature.ca.gov before relying on it. Educational information about California law, not legal advice.

Last reviewed: November 2026.