A percolation (“perc”) test measures how fast water drains through the soil on a California parcel. It's the key soil test that decides whether land without a sewer can support a septic system — and if you're buying rural or unimproved land in California, it's one of the most important due-diligence steps before you close. In California, septic systems are regulated as onsite wastewater treatment systems (OWTS) under the State Water Board's OWTS Policy and permitted parcel-by-parcel by your county environmental health department.
How a California perc test works
A tester digs one or more holes to the depth of a proposed leach field, presoaks them, then fills them with water and times how far the level drops — the result is the percolation rate in minutes per inch (MPI). Many California counties now pair or replace this with a soil-profile evaluation (a backhoe pit read by a professional) to check for restrictive layers, groundwater, and rock. The county uses the result to approve the site and size the leach field.
California-specific: it's a county program
California's OWTS Policy sets statewide minimums, but each of the state's 58 counties runs its own Local Agency Management Program — so the exact test method, acceptable perc range, witnessing rules, and wet-season requirement are set by your county, not a single statewide standard. Always confirm with the local environmental health department before testing or buying.
Reading perc test results: minutes per inch
A perc test result is a rate in minutes per inch (MPI): how many minutes the water level takes to fall one inch in the presoaked hole. Divide the minutes by the inches it dropped: 2 inches in 60 minutes is 30 MPI. A lower number means faster-draining soil. Soil that drains too fast filters wastewater poorly, and soil that drains too slowly cannot disperse it, so counties accept a range: many California counties accept roughly 1–120 MPI for a conventional system, with the exact range and the leach-field size for each rate set by the county. A result outside the range usually points to an engineered or alternative system rather than a conventional leach field.
Perc rate
minutes ÷ inches dropped
60 ÷ 2 = 30 MPI
Lower MPI = faster-draining soil. Your county sets the passing range.
Perc test vs. soil-profile evaluation: California's two accepted methods
Under the State Water Board's OWTS Policy, California counties evaluate a site with one or both of two methods. Which one your county requires — and whether it accepts a simple falling-head test or demands a professional soil-profile pit — is set in that county's Local Agency Management Program (LAMP).
| Method | What it measures | How California counties use it |
|---|---|---|
| Falling-head percolation test | How fast water drains, timed as minutes per inch (MPI) in a presoaked hole. | The traditional test; still accepted by many counties for conventional systems, usually with a required MPI range and multiple holes. |
| Soil-profile (morphological) evaluation | Soil texture and structure, restrictive layers, depth to rock, and seasonal high groundwater — read from a backhoe pit by a qualified professional. | Increasingly required (alone or alongside a perc test) under the OWTS Policy; it drives leach-field sizing and whether an engineered system is needed. |
The statewide trend is toward the soil-profile evaluation: a single drain-down time can miss a restrictive clay layer or a high water table that a profile pit reveals, so the OWTS Policy and most modern LAMPs favor reading the actual soil layers. Confirm which method your county accepts before you test.
Why it matters when buying California land
A parcel that can't pass a perc test may not be buildable with a conventional septic system — which dramatically affects its value and use. Make any purchase of unsewered California land contingent on a passing perc/soil test, and budget for the test plus the septic system and county permits. On a parcel with a well, the perc/leach field also has to meet setback distances from the well.
How long does a perc test take in California?
The fieldwork is usually a day or two: the holes are presoaked (saturated) before the timed readings, and hillside or complex sites need several holes. Add time to schedule the county inspector who witnesses it and for the professional's stamped report, and expect roughly one to three weeks from booking to results. Counties that require wet-season testing (roughly November to April, when groundwater is highest) may make you wait for the season, which is why land buyers should start early and make the purchase contingent on a passing test. The county table below shows which counties set a wet-season window.
What happens if your land fails a perc test?
A failed perc test does not always mean you cannot build. It usually means a conventional gravity leach field will not work. Depending on the county, you may still install an engineered or alternative system: a mound, an aerobic treatment unit (ATU), or a pressure-dosed or drip-dispersal field. These need an engineer's design and county approval and cost more (see septic system cost in California). Some parcels cannot support any system and are effectively unbuildable without a sewer connection, so a failed test is a major value and use question for a buyer. Soil type is the usual reason: check the parcel's soil and its septic-absorption rating on the California soil map before you buy.
What a perc test costs in California
The county's fee to review or witness a perc test runs $792–$1,515 in Humboldt, Sacramento, San Diego, Sonoma (published fee schedules); the consultant who digs and runs the test charges separately. A perc test itself is usually a modest line item next to the septic system it clears — but the total upfront cost to make an unsewered California parcel buildable is the test plus the county permit and the system. What California sources publish (verify with your county environmental health department, which sets its own fees):
| Item | California figure |
|---|---|
| County perc / soil review fee (Humboldt, Sacramento, San Diego, Sonoma) | $792–$1,515 |
| Consultant's fee to perform the test | not published by a California source |
| County septic permit and plan review, conventional (Los Angeles, Riverside, San Diego, Ventura) | $795–$1,846 |
| County septic permit and plan review, engineered or treated (same counties) | $1,114–$2,424 |
| New septic system, installed (Water Education Foundation, 2021) | $10,000–$25,000 |
| Engineered / alternative system, installed (mound, ATU, sand filter) | not published by a California source |
What drives the test cost: the number of test holes, whether a licensed engineer, geologist, or soil scientist must perform and stamp it, terrain (hillside and rocky sites cost more), and whether the county requires a full soil-profile pit. For the system side, see septic system cost in California.
A brief history of the perc test
The percolation test is generally credited to Henry Ryon, a sanitary engineer with the New York State Department of Health, who developed it in the 1920s to relate soil drainage to how large a septic leach field needed to be. It spread nationwide after the U.S. Public Health Service published it in the Manual of Septic-Tank Practice in the 1950s, which made “minutes per inch” the common yardstick for sizing a drain field.
By the late twentieth century, soil scientists criticized the falling-head test as too variable — the same hole can pass or fail depending on how it's dug, presoaked, and timed — which drove the shift toward reading the actual soil layers in a pit. California codified that modern approach in the State Water Resources Control Board's OWTS Policy (in effect since 2013): counties run Local Agency Management Programs and increasingly rely on soil-profile evaluations alongside, or instead of, the classic perc test. Knowing which era your county's rules sit in tells you whether to expect a simple perc test or a professional soil-profile evaluation.
Septic soil suitability by county
How much of each county's land the USDA soil survey rates as limited for a septic leach field. Statewide, 78% of mapped California land is rated “very limited” for septic tank absorption fields, mostly because of slope, shallow bedrock and slow-draining soils, and only 3.3% is “not limited”. That is why most rural parcels need a site evaluation, and some need an engineered system. Find your county below; for the parcel itself, read its rating in Web Soil Survey and order the county's test.
Key findings
The NRCS soil survey rates 78% of California's mapped land "very limited" for septic tank absorption fields and 3.3% "not limited"; slope is the most common limitation (54.3% of rated acres).
NRCS soil-survey ratings for septic tank absorption fields, acre-weighted over each county's mapped land; planning-scale map ratings, not a site test — the county decides from a soil profile or perc test on the parcel.
Data: SSURGO, queried 2026-11-03. Permalink
Among counties with at least 500,000 rated acres, the "very limited" share runs from 61.5% in Kern County to 96.8% in Imperial County.
NRCS soil-survey ratings for septic tank absorption fields, acre-weighted over each county's mapped land; planning-scale map ratings, not a site test — the county decides from a soil profile or perc test on the parcel.
Data: SSURGO, queried 2026-11-03. Permalink
45 of California's 58 counties operate an approved Local Agency Management Program (LAMP) for septic systems under the State Water Board's OWTS Policy.
Data: as read 2026-11. Permalink
Source: USDA NRCS Soil Survey Geographic (SSURGO) Database; county environmental health departments; State and Regional Water Boards. Computed from our dataset “Septic suitability by county (NRCS soil ratings, county site evaluation, LAMP status)” (version 2026-11-04); download the CSV. Free to reuse under CC BY 4.0. Findings update when the data does.
| Main limitations (share of rated acres) | County site evaluation | Septic program (LAMP) | ||||||
|---|---|---|---|---|---|---|---|---|
| California | 83,095,309 | 3.3% | 4.0% | 78.0% | 14.7% | slope 54%, depth to bedrock 41%, slow water movement 39% | — | — |
| Alameda | 530,244 | 0.1% | 2.7% | 67.2% | 29.9% | slope 50%, slow water movement 49%, depth to bedrock 41% | both (soil profile + perc) | Approved LAMP (5/21/2018) |
| Alpine | 502,750 | 0.0% | 0.4% | 88.7% | 10.8% | slope 90%, depth to bedrock 65%, seepage, bottom layer 45% | both: two test holes per dispersal site; 10-ft backhoe soil profiles (LAMP); code: 8-ft profiles + two perc tests on all lots | LAMP submitted |
| Amador | 374,227 | 0.0% | 1.4% | 85.4% | 13.2% | slope 84%, depth to bedrock 65%, slow water movement 30% | not verified, check the county | Approved LAMP (2/24/2017) |
| Butte | 1,400,204 | 0.0% | 1.5% | 79.4% | 19.1% | slow water movement 53%, slope 41%, depth to bedrock 38% | site evaluation required on every lot before an OWTS construction permit; percolation tests may be required (LAMP 19-6) | Approved LAMP (6/24/2016) |
| Calaveras | 1,052,993 | 0.0% | 0.4% | 86.1% | 13.6% | slope 79%, depth to bedrock 75%, slow water movement 42% | profile holes (minimum 4: 2 primary + 2 expansion, 6-8 ft deep) | Approved LAMP (8/11/2017) |
| Colusa | 738,831 | 0.0% | 4.9% | 93.7% | 1.4% | slow water movement 75%, flooding 50%, slope 39% | soil profiles + percolation tests (ordinance) | Approved LAMP (6/9/2017) |
| Contra Costa | 507,644 | 0.0% | 0.4% | 74.9% | 24.8% | slow water movement 58%, slope 50%, depth to bedrock 43% | both (soil profile + perc) | LAMP submitted |
| Del Norte | 119,962 | 0.0% | 2.6% | 90.2% | 7.2% | slow water movement 82%, slope 66%, depth to saturated zone 21% | backhoe excavation in primary and replacement area (one each); perc testing | LAMP submitted |
| El Dorado | 1,077,476 | 0.0% | 1.1% | 83.2% | 15.7% | slope 86%, depth to bedrock 62%, slow water movement 33% | site evaluation: soil pits + perc by consultant (reported, not confirmed) | Approved LAMP (6/9/2017) |
| Fresno | 4,536,431 | 0.3% | 6.2% | 76.7% | 16.8% | slope 53%, depth to bedrock 41%, slow water movement 37% | test hole inspection | Approved LAMP (4/6/2017) |
| Glenn | 866,673 | 0.0% | 4.2% | 79.7% | 16.2% | slow water movement 56%, slope 46%, depth to bedrock 38% | both: >=3 perc tests per primary and replacement area (6 if not contiguous); >=1 excavation in primary and replacement area | Approved LAMP (4/7/2017) |
| Humboldt | 2,049,386 | 0.0% | 0.9% | 95.2% | 3.9% | slow water movement 91%, slope 90%, depth to saturated zone 20% | site evaluation: soil profiles; wet-weather perc for Zone 3/4 clay soils (reported, not confirmed) | Approved LAMP (2/8/2018) |
| Imperial | 990,051 | 0.1% | 2.3% | 96.8% | 0.7% | slow water movement 62%, depth to saturated zone 42%, filtering capacity 37% | soil evaluation: minimum 3 test holes, at least 8 ft deep; tests older than 5 yrs must be redone | Approved LAMP (6/30/2016) |
| Inyo | 1,774,420 | 12.4% | 5.3% | 81.9% | 0.5% | slope 52%, depth to bedrock 49%, slow water movement 19% | both: 10-ft soil profiles + perc tests (generally 2 + 2 in construction area, 1 + 1 in replacement); leach lines limited to <=120 MPI | Approved LAMP (7/19/2018) |
| Kern | 6,171,584 | 9.9% | 14.0% | 61.5% | 14.6% | slow water movement 37%, slope 37%, flooding 26% | perc test required for every leach-line application (QP) | Approved LAMP (6/9/2017 6/17/2021) |
| Kings | 919,203 | 10.4% | 6.4% | 68.2% | 15.0% | slow water movement 63%, flooding 35%, depth to saturated zone 32% | not verified, check the county | Approved LAMP (5/31/2018) |
| Lake | 920,657 | 0.0% | 0.0% | 76.9% | 23.1% | slope 73%, depth to bedrock 64%, slow water movement 41% | site evaluation by Environmental Health before a septic permit application; evaluates effective soil depth, lot size and depth to groundwater; soil profiles from test pits | Tier 1 (no LAMP) |
| Lassen | 3,673,725 | 0.8% | 2.2% | 91.1% | 5.9% | slope 70%, depth to bedrock 69%, slow water movement 51% | both: >=3 perc test holes per dispersal location; >=2 backhoe excavations >=8 ft; minimum 2 soil profiles per OWTS | LAMP submitted |
| Los Angeles | 2,917,708 | 0.1% | 2.2% | 81.3% | 16.3% | slope 72%, seepage, bottom layer 36%, slow water movement 27% | both (feasibility report needs perc test data AND geologist-logged soil profile) | Approved LAMP (5/21/2018) |
| Madera | 965,198 | 0.2% | 5.6% | 73.4% | 20.7% | slow water movement 37%, slope 37%, seepage, bottom layer 31% | not verified, check the county | Approved LAMP (4/7/2017) |
| Marin | 389,843 | 0.2% | 1.3% | 62.0% | 36.5% | slope 57%, depth to bedrock 52%, slow water movement 34% | not verified, check the county | LAMP submitted |
| Mariposa | 881,942 | 0.0% | 1.0% | 71.6% | 27.4% | slope 89%, depth to bedrock 53%, slow water movement 28% | percolation tests (minimum 4 per lot, ~50 ft apart); 5-60 min/inch range for standard design | Approved LAMP (4/7/2017) |
| Mendocino | 2,361,911 | 0.0% | 1.1% | 78.9% | 20.0% | slope 82%, slow water movement 64%, depth to bedrock 54% | perc testing required for all Zone 3 soils (Technical Standards, BOS attachment) | Approved LAMP (11/4/2018) |
| Merced | 1,263,499 | 0.6% | 4.0% | 79.5% | 15.8% | slow water movement 56%, depth to saturated zone 27%, depth to bedrock 19% | site evaluation by qualified professional: perc tests, soil profiles, soil suitability/nitrate loading studies | Approved LAMP (4/7/2017) |
| Modoc | 1,233,866 | 1.7% | 3.7% | 75.3% | 19.3% | slow water movement 47%, slope 40%, depth to bedrock 39% | soil profiles from applicant-provided test pits (LAMP) | Approved LAMP (2/24/2017) |
| Mono | 1,038,495 | 1.2% | 5.4% | 87.5% | 5.9% | slope 71%, depth to bedrock 47%, seepage, bottom layer 34% | both: >=2 test trenches >=10 ft deep + >=2 perc tests in disposal area | Approved LAMP (7/19/2018) |
| Monterey | 2,169,834 | 1.1% | 1.0% | 75.5% | 22.4% | slope 65%, depth to bedrock 54%, slow water movement 40% | feasibility report: >=1 deep GW boring + soil profile + perc in primary and expansion areas (reported, not confirmed) | Approved LAMP (2018-05-10) |
| Napa | 462,086 | 0.0% | 4.1% | 88.2% | 7.7% | slope 75%, depth to bedrock 67%, slow water movement 56% | site evaluation: backhoe test pits to 5 ft or bedrock, >=24 in. wide, covering primary and reserve areas; soils must be dry; percolation results submitted with Test Pit Log | LAMP submitted |
| Nevada | 1,358,715 | 0.0% | 0.1% | 84.5% | 15.3% | slope 93%, depth to bedrock 74%, slow water movement 38% | On-Site Soils Evaluation (OSSE) by a Soil Testing Consultant, reviewed by county Environmental Health Specialist (Findings Report runs with the land); recertification required for reports >3 years | Approved LAMP (4/7/2017) |
| Orange | 504,803 | 0.1% | 9.5% | 75.9% | 14.4% | slope 45%, slow water movement 44%, depth to bedrock 37% | perc test (6 tests for leach field; >=1 for seepage pit) + exploratory boring | Under review (not yet approved) |
| Placer | 600,304 | 0.3% | 1.9% | 73.5% | 24.2% | slope 54%, depth to bedrock 45%, slow water movement 38% | on-site soil evaluation (soil profiles; perc when needed) | Approved LAMP (4/7/2017) |
| Plumas | 1,871,919 | 0.0% | 1.1% | 83.2% | 15.7% | slope 78%, depth to bedrock 71%, slow water movement 36% | perc test required on every lot with tank + leach system | Approved LAMP (2/24/2017) |
| Riverside | 2,829,242 | 1.1% | 5.2% | 73.3% | 20.4% | slope 50%, depth to bedrock 36%, filtering capacity 23% | perc test (4 passing + 1 deep boring for leach field; 2 + boring for pits) by registered PR | Approved LAMP (11/17/2016) |
| Sacramento | 638,060 | 9.0% | 0.8% | 73.1% | 17.1% | slow water movement 54%, depth to cemented pan 36%, depth to saturated zone 26% | test drill/soil study witnessed by EMD; engineered perc if it fails | Approved LAMP (12/11/2015) |
| San Benito | 889,358 | 0.0% | 5.1% | 84.2% | 10.7% | slope 82%, depth to bedrock 71%, slow water movement 47% | not verified, check the county | LAMP submitted |
| San Bernardino | 10,899,861 | 14.0% | 3.8% | 75.8% | 6.3% | filtering capacity 40%, slope 33%, depth to bedrock 26% | perc test report (QP; 2 business days notice) | Approved LAMP (7/13/2017) |
| San Diego | 2,339,051 | 2.5% | 2.0% | 82.0% | 13.6% | slope 69%, depth to bedrock 57%, seepage, bottom layer 34% | either/both (percolation test / soil profile review) | Approved LAMP (2024 (Res. R9-2024-0130); 2015-04-29 original) |
| San Francisco | 45,238 | 21.8% | 0.2% | 33.3% | 44.6% | slope 30%, filtering capacity 9%, seepage, bottom layer 9% | no OWTS program - county is fully sewered; not applicable | n/a (sewered) |
| San Joaquin | 912,730 | 0.3% | 5.4% | 76.8% | 17.6% | slow water movement 58%, flooding 40%, depth to saturated zone 36% | both (perc test permit + soil profile >=10 ft where GW/clay unknown) | Approved LAMP (4/7/2017) |
| San Luis Obispo | 1,592,520 | 0.1% | 0.8% | 73.5% | 25.6% | slope 62%, depth to bedrock 53%, slow water movement 43% | perc test (>=4 holes) by registered engineer/geologist/REHS; results valid 1 yr | LAMP submitted |
| San Mateo | 373,725 | 7.7% | 1.0% | 56.7% | 34.6% | slope 50%, slow water movement 41%, depth to bedrock 39% | soil profile + perc per Section 2 site investigation | Approved LAMP (2022-03 (approval letter)) |
| Santa Barbara | 1,226,099 | 0.2% | 3.0% | 81.0% | 15.8% | slope 66%, depth to bedrock 46%, slow water movement 43% | soil percolation report by registered civil or soils engineer (re-certify if >5 yrs old) + deep boring log | Approved LAMP (2015-11-20) |
| Santa Clara | 849,746 | 0.0% | 0.6% | 79.9% | 19.4% | slope 71%, depth to bedrock 57%, slow water movement 34% | both (soil profiles in primary+reserve area; perc test) | Approved LAMP (2014-07) |
| Santa Cruz | 276,152 | 0.4% | 0.2% | 86.4% | 13.0% | slope 76%, depth to bedrock 64%, slow water movement 46% | site evaluation: soil profile + perc + groundwater as EH determines | Approved LAMP (2021-10-14) |
| Shasta | 1,819,782 | 0.0% | 2.2% | 84.0% | 13.7% | slope 70%, depth to bedrock 55%, slow water movement 41% | perc test required to size leach field (reported, not confirmed) | Approved LAMP (10/20/2017) |
| Sierra | 263,352 | 2.2% | 0.1% | 83.3% | 14.4% | slow water movement 48%, slope 47%, depth to bedrock 34% | both: >=1 test pit per lot (2 ft wide, 5 ft deep, QP-logged); >=3 perc tests (4 if >60 MPI) | Approved LAMP (8/2/2018) |
| Siskiyou | 1,365,296 | 0.4% | 3.1% | 77.7% | 18.8% | slow water movement 53%, slope 52%, depth to bedrock 45% | perc test (county method form); wet-weather evaluation for some parcels | LAMP submitted |
| Solano | 581,984 | 0.4% | 1.5% | 77.0% | 21.1% | slow water movement 63%, flooding 37%, depth to saturated zone 28% | both: >=1 backhoe excavation in primary and replacement field (>=8 ft); >=3 perc holes per field and reserve | Approved LAMP (8/19/2016) |
| Sonoma | 1,032,035 | 0.0% | 2.3% | 82.8% | 14.9% | slope 66%, slow water movement 62%, depth to bedrock 60% | soil profile evaluation/pre-perc + percolation | Approved LAMP (6/16/2026) |
| Stanislaus | 990,370 | 0.0% | 12.2% | 75.8% | 12.0% | slow water movement 51%, depth to bedrock 40%, slope 35% | perc test (3-5 eight-inch holes for leach lines); acceptable 1-120 MPI; soil evaluation only for extreme soils or engineered designs | Approved LAMP (6/9/2017) |
| Sutter | 391,634 | 0.2% | 3.1% | 77.5% | 19.2% | slow water movement 68%, flooding 51%, depth to saturated zone 45% | soil and site evaluation before construction (Ord. 1632 sec. 700-090); perc and/or hydrometer tests for type 5 and 6 soils, at least 3 per primary and replacement area (700-110) | Approved LAMP (8/11/2017) |
| Tehama | 1,881,327 | 0.0% | 2.8% | 81.6% | 15.6% | slope 65%, depth to bedrock 54%, slow water movement 36% | both: >=1 test pit per lot (2 ft wide, 8 ft deep); 3 representative perc tests | Approved LAMP (6/9/2017) |
| Trinity | 290,510 | 0.0% | 1.3% | 85.9% | 12.7% | slope 85%, slow water movement 69%, depth to bedrock 50% | perc tests submitted with application; profile hole may be required to show groundwater | LAMP submitted |
| Tulare | 1,687,412 | 0.0% | 10.0% | 65.0% | 25.0% | slow water movement 56%, flooding 40%, slope 33% | not verified, check the county | Approved LAMP (4/5/2018) |
| Tuolumne | 2,105,721 | 0.0% | 0.2% | 74.1% | 25.7% | slope 81%, depth to bedrock 58%, slow water movement 29% | soil profile/texture survey for each new installation; percolation tests not always required; >=5 ft permeable soil below trench (reducible to 2 ft per Guidelines) | Approved LAMP (4/5/2018) |
| Ventura | 516,460 | 0.0% | 7.2% | 78.0% | 14.8% | slope 55%, slow water movement 52%, depth to bedrock 48% | perc test + soils report | Approved LAMP (2018-05-04) |
| Yolo | 658,822 | 0.6% | 1.5% | 81.9% | 16.0% | slow water movement 71%, flooding 40%, slope 27% | soil profile study (pits at least 8 ft deep); perc tests supplemental | Approved LAMP (8/19/2016) |
| Yuba | 412,236 | 0.0% | 2.3% | 77.7% | 19.9% | slow water movement 60%, slope 41%, depth to bedrock 40% | site evaluation with at least two soils test pits; percolation tests typically required before a site evaluation report (OWTS Manual ch. 2) | Approved LAMP (5/31/2018) |
Shares of each county's mapped (rated) acres by the NRCS “Septic Tank Absorption Fields” rating, weighted by map-unit acres; “not rated” covers water, urban land and other areas the survey does not rate. “Rated acres” is the land the survey rates in that county. “Main limitations” are the reasons NRCS gives most often, each with the share of rated acres it applies to; one acre can carry several reasons, so the shares overlap and do not add to 100%. Click a column heading to sort. These are planning-scale map ratings, not a site test: your county decides from a soil profile or perc test on the parcel. County site evaluation: the county's stated requirement where we could verify it; “not verified” means we have not confirmed it yet. Sources: Soil Survey Staff, Natural Resources Conservation Service, USDA. Soil Survey Geographic (SSURGO) Database for California (Soil Data Access), accessed 2026-11-03. State Water Resources Control Board and Regional Water Boards, OWTS Local Agency Management Program status. Download: septic-suitability-by-county.csv (public-domain source data).
What the 15 largest counties require: soil profile, perc test, wet-season rules and fees
Each county's environmental-health office runs its own onsite wastewater (OWTS) program under the State Water Board's OWTS Policy and the county's Local Agency Management Program, so the test you need depends on the county. The table summarises California's 15 most populous counties as their published guidance read on November 1, 2026: whether a geologist-logged soil profile, a falling-head percolation test, or both are required; any wet-season or groundwater rule; and the fee the county charges to review or witness the site evaluation. San Francisco is fully sewered and has no OWTS program.
| County | What is required | Wet-season / groundwater rule | Fee for the site evaluation |
|---|---|---|---|
| Los AngelesLA County DPH Environmental Health - Land Use Program | both (feasibility report needs perc test data AND geologist-logged soil profile) | none fixed; perc start delayed 3 weeks after >=2 in. rain in 10 days; site-specific seasonal/historical groundwater determination required | $167/hr (perc evaluation; hourly) (FY 2025-26) — reported, not confirmed |
| San DiegoCounty DEHQ Land & Water Quality Division | either/both (percolation test / soil profile review) | none fixed; groundwater boring checked >=72 h after drilling; wet-weather monitoring may be required in high-groundwater areas | $792 (FY 2026-27) |
| OrangeOC Public Works (perc review) / OC Health Care Agency | perc test (6 tests for leach field; >=1 for seepage pit) + exploratory boring | none fixed (presoak simulates wettest season); exploratory boring >=5 ft below system for groundwater | not published / not found |
| RiversideCounty DEH Land Use & Water Resources | perc test (4 passing + 1 deep boring for leach field; 2 + boring for pits) by registered PR | none fixed; groundwater detection boring | $199/hr site evaluation |
| San BernardinoCounty EHS Land Use & Wastewater | perc test report (QP; 2 business days notice) | not published | $464 (SFD perc report review) |
| Santa ClaraCounty DEH Land Use | both (soil profiles in primary+reserve area; perc test) | wet-weather testing during wet season when shallow groundwater likely (exact dates not found); wet-weather groundwater investigation; wet-weather perc for high-clay soils | not published / not found |
| AlamedaACEH Land Use Program | both (soil profile + perc) | not published; wet-weather groundwater investigation as applicable | $721 soil profile + $433 perc — reported, not confirmed |
| SacramentoCounty EMD Liquid Waste | test drill/soil study witnessed by EMD; engineered perc if it fails | not published | $1,505 (test drill/soil study) (FY 2025-26) |
| Contra CostaContra Costa Health EH Land Use | both (soil profile + perc) | wet-weather period (dates not found); groundwater observations (3 on separate days >=7 days apart) on flat/high-GW sites; wet-weather perc for clay soils | $604 perc / $514 soil profile — reported, not confirmed |
| FresnoCounty DPH Environmental Health | test hole inspection | not published | $71.87 per test-hole inspection w/ septic permit (2023-24) — reported, not confirmed |
| KernKern County Public Health EHS | perc test required for every leach-line application (QP) | not published | not published / not found |
| San Franciscono OWTS program | no OWTS program - county is fully sewered; not applicable | n/a | n/a |
| VenturaCounty RMA Environmental Health | perc test + soils report | not published; highest historical groundwater evaluation required | no separate perc fee; $1,273 conventional application (FY 2026-27) |
| San MateoSan Mateo County Health EH Land Use | soil profile + perc per Section 2 site investigation | wet season (dates not found); wet-weather groundwater testing when seasonal high GW not shown by soil | $960 wet-weather groundwater testing — reported, not confirmed |
| San JoaquinCounty EHD Liquid Waste | both (perc test permit + soil profile >=10 ft where GW/clay unknown) | not published | charged hourly, rate not published |
Sources: each county's OWTS guidance, Local Agency Management Program and fee schedule, as published; retrieved November 1, 2026. “Reported, not confirmed” marks a fee quoted from a county page that could not be opened in full (Alameda, Contra Costa, Fresno, Los Angeles, San Mateo); “not published” means the county did not post the item where its guidance points. None of the 15 publishes a fixed wet-season window: Contra Costa, Santa Clara and San Mateo require wet-weather groundwater testing with dates set each season, and Los Angeles delays a perc test three weeks after two inches of rain in ten days. Download the table: CSV (CC BY 4.0), which carries the source links. Verify with the county before scheduling a test.
Perc tests and soil pits in the Sierra foothills
In the USDA soil survey, depth to bedrock is the most common septic limitation after slope in the foothill counties: it applies to 44.7–74.5% of rated acres across Amador, Calaveras, El Dorado, Mariposa, Nevada, Placer and Tuolumne. That is why these counties look at the soil mantle (the layer of usable soil above bedrock or groundwater) as well as at percolation, and why land listings there sometimes say “perc and mantle”. Nevada and Tuolumne counties use the term in their own documents. What each county requires, in its own words:
- Calaveras County: “A minimum of four (4) profile holes are required … Two (2) profile holes shall be dug in the proposed sewage disposal area and two (2) in the proposed expansion area. Profile holes shall be 2' to 3' in width and 6' to 8' in depth.” “An OWTS permit will not be issued until a profile hole application has been issued and a plan has been approved.” (county source)
- Mariposa County: “Four (4) percolation tests per lot minimum will be required. Tests shall be conducted approximately 50' apart and must be conducted within an area that is naturally suitable from a slope, setback and available area standpoint.” (county source)
- Placer County: “Soils testing is conducted by a sewage disposal consultant and a representative of Environmental Health. Results of the testing will determine the type, location, and site of the septic system.” A parcel without a soils testing report needs one “to make sure the parcel can be developed.” (county source)
- Nevada County: “Before applying for a new septic system, it is necessary to have valid soils testing done.” The On-Site Soils Evaluation (OSSE) “includes soil tests that determine the effectiveness of soil to filter sewage through leach lines, as well as observations of required setbacks, constraints, future repair area”; the county's soil mantle log records each pit's slope, soil horizons, effective soil depth and groundwater. (county source)
- Tuolumne County: “Because a good indicator of soil permeability is the texture and structure of the soil mantle (which is surveyed for each new installation), percolation tests are not always required.” “There shall be a minimum of five feet of permeable soil below the bottom of a leach trench or bed.” (county source)
El Dorado and Amador County pages could not be opened to confirm their wording; ask the county environmental health department. Each county's share of land rated very limited for septic is in the suitability table. Accessed November 4, 2026.
Frequently Asked Questions
What is a perc test in California?
A percolation ("perc") test measures how quickly water drains through the soil on a parcel. In California it's the core soil evaluation used to decide whether land without a sewer connection can support a septic system — an onsite wastewater treatment system (OWTS) — and, if so, how big the leach field must be. Your county environmental health department requires it before issuing a septic permit for new construction.
How much does a perc test cost in California?
Two separate charges. The county's fee to review or witness the test is published: $792–$1,515 in Humboldt, Sacramento, San Diego, Sonoma (fiscal 2025-26 and 2026-27 schedules), and the county table on this page lists 15 counties. The consultant's price to dig the holes and run the test is not published by any California agency; it depends on how many holes the county requires, whether a licensed engineer, geologist or soil scientist must stamp it, and the terrain, so get quotes. The septic permit and the system are separate costs.
Who performs a perc test in California?
Most California counties require a qualified professional — a Registered Environmental Health Specialist, civil engineer, professional geologist, or soil scientist — to conduct the test, and a county inspector often witnesses it. A few counties allow property-owner testing for simple sites, but the trend under the State Water Board's OWTS Policy is toward professional soil-profile evaluations.
What is a passing perc rate?
Perc rate is measured in minutes per inch (MPI) — how long the water level takes to drop one inch. Soil that drains too fast filters wastewater poorly; soil that drains too slowly can't disperse it. Many California counties accept roughly 1–120 MPI for a conventional system, with the exact acceptable range and required leach-field sizing set by the county. Outside that range you may still build with an engineered/alternative system (mound, ATU), which costs more.
When can you do a perc test in California?
Some California counties require testing during the wet season (roughly November–April) when the seasonal high groundwater is nearest the surface, because that's the worst-case condition for a septic system. Others allow year-round testing. Check your county environmental health department's schedule before you buy land — a failed or out-of-season test can stall a purchase.
Do I need a perc test if the property has sewer or an existing septic?
No. A perc test is only for new onsite systems. If the parcel is connected to a public sewer you don't need one, and if it has a permitted existing septic system you generally only need a perc/soil test when adding bedrooms, a second unit (such as an ADU), or replacing/expanding the system.
How long does a perc test take, and when do you get results?
The fieldwork is usually done in a day, but a proper test often runs over a day or two because the holes must be presoaked (saturated) before the timed drop is measured, and hillside or complex sites need several holes. Add time for scheduling the county inspector to witness it and for the professional's stamped report — expect roughly one to three weeks end-to-end. In counties that require wet-season (roughly November–April) testing, you may have to wait for the season, which is why land buyers should start early and keep the purchase contingent on a passing test.
What happens if a perc test fails in California?
A failed perc test doesn't always mean you can't build — it usually means a conventional gravity leach field won't work. Depending on the county, you may still be able to install an engineered or alternative onsite system (a mound system, an aerobic treatment unit (ATU), a pressure-dosed or drip-dispersal field), which costs more and needs an engineer's design and county approval. Some parcels can't support any system and are effectively unbuildable without sewer, so a failed test is a major value and use issue — see typical system costs on the septic system cost page.
Does my county require a perc test, a soil profile, or both?
It depends on the county's OWTS program. Of California's 15 most populous counties, Los Angeles, San Diego, Santa Clara, Alameda, Contra Costa, San Joaquin require both a logged soil profile and a percolation test; Orange, Riverside, San Bernardino, Sacramento, Kern, Ventura, San Mateo centre their requirement on the percolation test (with an exploratory or groundwater boring); San Diego accepts a percolation test or a soil-profile review; Sacramento witnesses a test drill and soil study and asks for an engineered perc test only if that fails; San Francisco is fully sewered and has no program. The table above gives each county's wording and the fee it charges, as published on November 1, 2026.
Learn More
California-specific educational overview, not engineering or legal advice, and not a substitute for your county's requirements. Septic/OWTS rules are set by the California State Water Resources Control Board (OWTS Policy) and administered by county environmental health departments; some public-health rules also involve the California Department of Public Health. Confirm the current process, fees, and acceptable perc rates with your county before acting.